1 The group company is responsible for guiding each member unit and project department to simulate the accident state according to the dangerous target, and formulate the emergency disposal plan under various accident States, such as formwork support collapse, large equipment collapse, foundation pit collapse, electric shock, personnel poisoning, toxic gas leakage, combustion, explosion, water cut, power cut, etc., including communication, emergency rescue, medical rescue, emergency treatment, etc Casualty transfer, personnel evacuation, proction system command, report and contact, rescue action plan, etc
(2) the group company is responsible for guiding the company (branch company) and the project department to formulate the accident handling procere chart. In case of an accident, the group company shall operate in a fast, effective and orderly manner according to the emergency plan, so as to ensure correct command in the face of danger. After the accident, under the unified command of the leading group, according to the assessment of the potential danger of the dangerous target, the accident should be handled and controlled in an orderly way according to the disposal plan. Neither panic nor carelessness should be allowed, and the accident should be controlled in the minimum range as far as possible to minimize casualties and property losses(3) in the event of an accident, which may pose a danger to the safety of people inside and outside the area, under the command of the leading group, the personnel unrelated to the accident emergency rescue shall be evacuated. When it may threaten the safety of residents (including the personnel of neighboring units), the leading group shall immediately contact the relevant local departments to guide the residents to evacuate to a safe place
after the accident, emergency measures should be taken to prevent the further expansion of the accident and the increase of casualties, as well as the occurrence of secondary accidents
(4) effective engineering rescue and repair is the key to control and eliminate accidents. According to the plan drawn up in advance and on the basis of indivial prevention, the rescue personnel should eliminate the accident in time with the fastest speed (5) in case of any accident, such as foundation pit collapse, formwork support collapse, object strike, etc., the project department shall spare no effort to rescue the wounded at all costs, and report it to the member unit where it works, and the member unit shall report it to the group company, and start the emergency plan according to the accident level after receiving the report. Ask for social assistance when necessary. The leading group shall send special personnel to contact, guide and inform the safety precautionsit is not allowed to move the falling and fracture personnel at will, but it should be carried with stretcher template; The wounded with gas poisoning and suffocation should be ventilated as soon as possible to let them breathe fresh air; Patients with chemical poisoning should be injected with special antidote or given necessary medical treatment before being transferred to various hospitals according to the degree of poisoning and injury
in case of electric shock, the power supply must be cut off before contacting the injured person, so as to avoid multiple casualties caused by continuous electric shock. If the injured person has bleeding, stop bleeding as much as possible
when a major mechanical equipment accident occurs on site, the director of the project department should first judge whether there is the possibility of further development of the situation, and immediately inform the relevant departments to organize forces for protection and rescue, control the development of the situation, and minimize the losses caused by the accident
(6) strengthen the training of rescue teams. The leading group should proceed from reality and organize simulation exercises at least once a year for key areas, parts, processes and equipment, so as to train each rescue group into a command group and rescue team with good thinking, excellent technology and hard work style. Once an accident occurs, each rescue team can timely and effectively eliminate the danger, control and eliminate the accident, rescue the wounded and do a good job in emergency rescue according to their respective tasks (7) after the accident happened at the scene, we should pay special attention to stabilize the staff's mood and carry out accident prevention ecation for all staff (8) conscientiously implement the regulations of the State Council on the reporting and handling of casualty accidents of enterprise employees, do a good job in the investigation and handling of casualty accidents, and strictly implement the principle of "four don't let go"
extended materials:
the significance of safe proction:
safe proction is the consistent guiding ideology and important policy of the party and the state in proction and construction, and is the inevitable requirement of comprehensively implementing the scientific outlook on development and building a socialist harmonious society. The fundamental purpose of safe proction is to ensure the safety and health of workers in the proction process. Safety proction is the unity of safety and proction. Safety promotes proction and proction must be safe
without safety, normal proction cannot be carried out. To do a good job in proction safety, improve working conditions and rece casualties and property losses of employees can not only improve enterprise efficiency and promote the healthy development of enterprises, but also promote social harmony and ensure the safety of economic construction< br />
I. General principles
L. all employees of our company must seriously study, implement and implement the policy of safe proction, model and abide by the national laws and regulations on safe proction, and earnestly implement the company's regulations on safe proction and fire management, so as to ensure the personal safety and physical and mental health of employees in the proction process. Ensure the security of state property and collective property
2. To do a good job in proction safety and fire safety, prevention should be the main task. Proction safety and fire safety must be emphasized every year, every month and every day. To make all staff fully aware of the importance of doing a good job in proction safety and fire safety, to fully understand the importance of doing a good job in prevention, to eliminate all kinds of potential safety hazards, to eliminate all kinds of accidents in the bud! We should strengthen the ecation and training of workers in safety proction, and form a good situation in which everyone understands safety knowledge and manages safety
3. In order to deal with all kinds of sudden major accidents, it is necessary to formulate a practical and feasible spiritual principle of "emergency response and rescue plan", and deal with these accidents in an orderly way, so as not to be in a hurry and delay the fight. For this reason, the "emergency response and rescue plan for major accidents" is formulated
4. All employees of our company are required to be familiar with the specific requirements of the rescue plan, and everyone can flexibly command at the scene of the accident and properly handle all kinds of accidents according to the requirements of the plan< In case of a sudden major accident, the top leader at the scene of the accident is the commander in chief of the accident
2. The on-site commander in chief must be calm, resolute and resolute in handling matters, and immediately organize the rescue work according to the spirit of the rescue plan. Don't delay the best time for rescue
3. Based on the principle of "rescue first and report later", the on-site commander in chief should first organize the on-site staff to carry out rescue work, and report to the company leaders immediately after controlling the situation
4. Once the on-site situation is out of control and the company leaders cannot be contacted, the on-site commander in chief has the right to deal with all kinds of emergencies:
(1) in case of fire, call 119 for help immediately
(2) in case of personal injury and death, if the vehicle cannot be found at the moment, the emergency center of 120 city should be immediately rescued
5. In the event of an accident, all on-site staff should actively participate in the rescue work under the leadership of the on-site commander in chief. They should never retreat, become deserters, or refuse to obey the leadership to delay the fight. Once such incidents occur, the company will investigate the responsibility and seriously deal with them< After a fire accident, the team leader of the accident team shall immediately organize the team members to put out the fire, and shall not delay the fire fighting work for any reason
2. After a sudden fire accident, the non accident team operators should, depending on the severity of the fire at that time and under the unified dispatch of the on-site fire fighting commander in chief, send some personnel to help put out the fire, or take emergency power-off measures to send all personnel to help put out the fire< 4. Emergency treatment and rescue plan for personal injury accident
1. In case of a major personal injury accident, the team leader and on-site operators should take decisive measures to stop the machine or cut off the power immediately to rescue the victim from the machine or the electric shock
2. If the victim loses a lot of blood, the on-site commander should immediately organize the staff to temporarily bind and stop bleeding
3. If the victim stops breathing and heartbeat, the victim should be moved to an open space immediately, and artificial respiration and cardiac compression resuscitation should be implemented without delay
4. At this time, the on-site commander should seize the time, make an immediate decision, and ask 120 emergency center for help
5. The on-site commander should report to the company leaders in time
6. In case of general personal injury accidents, the on-site commander in chief should immediately report to the company leaders and find a car to send the victims to the hospital for treatment
7. When dealing with personal injury accidents, the on-site commander should deal with them promptly and safely without delay! Don't delay the best time to treat the victims! Time is life< 5. Emergency treatment and rescue plan for equipment accident
1. In case of a major equipment accident, the team leader should take measures quickly to shut down the machine and cut off the power to prevent the accident from expanding
2. If personal injury accident occurs e to equipment accident, rescue people immediately. After rescuing the victim, start the procere of "emergency treatment and rescue plan for personal injury accident" immediately, and then deal with the equipment accident
3. After a major equipment accident, if it is not e to special circumstances such as saving people, try not to move all kinds of objects on the site, and protect the site to analyze the cause of the accident
4. After a major equipment accident, if "move" or "support" is not taken quickly; If the accident is likely to expand or endanger personal safety, the on-site commander can take these measures to deal with it. However, detailed records should be made and explained to the accident investigators so as to accurately determine the cause of the accident
5. After a major equipment accident occurs, the on-site commander should immediately report to the company leaders in case of emergency treatment< When an accident occurs, the implementation of the accident plan is completed by the emergency rescue system. The emergency rescue system is divided into two parts: the headquarters and the professional team. The chief commander of the headquarters shall be the legal representative of the enterprise. Command members should include factory proction, equipment, fire fighting and medical personnel who have the ability, responsibility, power and resources to complete a certain task. The members of the headquarters directly lead the subordinate first aid professional teams and are responsible to the General Commander, who coordinates the work of each team
telephone number of company leaders:
General Manager: General Commander of the headquarters: telephone number:
Deputy General Commander of the headquarters: telephone number:
members of the headquarters: telephone number:
members of the headquarters: telephone number:
the professional team is composed of workshop supervisors. Professional team: once the accident happens, the organization rush to the scene of the accident, and implement the emergency rescue plan at the scene and the first line
it can be divided into communication teams according to tasks: to ensure the smooth broadcasting and communication between the professional teams and the general control room and the headquarters; Guide the evacuation and self rescue of personnel through broadcasting
number: 5 Team Leader:
member list:
equipment: walkie talkie, telephone, mobile phone, loudspeaker, alarm
public security team: maintain public security in the plant area, and evacuate people and vehicles in a planned way according to the development trend of the accident
number of people: 4 team leader:
member list:
equipment: walkie talkie, telephone, mobile phone, tweeter, sign board
rescue and repair team: members of the team should be familiar with the accident site, equipment and process, and repair the equipment under the premise of protective measures, so as to prevent the expansion of the accident, rece the accident loss and inhibit the expansion of the scope of harm
number: 2 Team Leader:
member list:
equipment: protective gloves, repair tools, etc
the professional team is composed of workshop supervisors. Professional team: once the accident happens, the organization rush to the scene of the accident, and implement the emergency rescue plan at the scene and the first line< 7. The emergency response and rescue plan for major accidents is the basic principle for all employees of our company in dealing with sudden major accidents. All cadres and employees of the company are required to follow the example and implement it firmly. Those who have modification opinions and supplementary opinions on the plan shall submit them to the leaders of the company as soon as possible, so that the company can timely modify the plan after summarizing the opinions.
the purpose of making a fire emergency plan is to make a unified command, timely and effectively integrate human resources, material resources, information and other resources in the face of a sudden fire accident, quickly implement organized control and fighting against the fire, avoid confusion and disorder at the scene of the fire, and prevent the delay of fighters and the loss of control, Minimize casualties and property losses basic principles
the plan must follow the following principles
1 prevention first principle
2 timely alarm principle
3 timely fire fighting principle
4 key protection principle
, organize fire prevention leading group unit to establish fire safety emergency headquarters, which is responsible for the company's fire scene command, Fire safety
the whole emergency headquarters is composed of unit leaders and members of security and relevant departments (units) in charge of the unit; It is strictly forbidden to use open fire for heating, burning and connecting open lines with electricity. Water heater, computer, TV,
lamps and other electrical appliances should be turned off as soon as they are used, and the power should be cut off in time. Fire prevention management shall be strengthened for key parts, sufficient fire-fighting equipment shall be provided, and the area plan marked with fire-fighting equipment layout point and safety passage shall be posted in a conspicuous position. Keep the water source unblocked at all times
When a fire occurs, the type of fire (electric fire, fire of dangerous goods, fire of inflammables) and the size of fire should be determined. For the fire that can be put out immediately, we should seize the opportunity to quickly eliminate it. For the fire that cannot be put out immediately, the principle of "control first, then eliminate" shall be adopted. The spread of the fire shall be controlled first, and the fire prevention leading group shall immediately report to the fire prevention leading group. The fire prevention leading group shall start the fire prevention emergency plan and quickly organize the existing personnel to implement the following work in a timely manner; Immediately dial the fire telephone "119" to inform the fire department. When calling the police, it is necessary to state the fire type, fire intensity and contact number. Send someone to the intersection to receive the alarm and instruct the fire passage 2. Cut off the power supply, transfer valuables, inflammables and explosives to avoid causing a second fire. Actively take fire fighting measures and do not delay the time of fire fighting
4, Organize children, the elderly and women to escape and evacuate, maintain order and count the number of people, find out whether there are people trapped in the fire and what important materials need to be evacuated, and inform the fire commander of the situation in time
Accident emergency rescue plan:
I. General principles
L. all employees of our company must seriously study, implement and implement the policy of safe proction, exemplary abide by the national laws and regulations of safe proction, and conscientiously implement the company's regulations on safe proction and fire management, so as to ensure the personal safety and physical and mental health of employees in the proction process. Ensure the security of state property and collective property
It is necessary to take prevention as the main task to do a good job in proction safety and fire safety. Proction safety and fire safety must be emphasized every year, every month and every day. To make all staff fully aware of the importance of doing a good job in proction safety and fire safety, to fully understand the importance of doing a good job in prevention, to eliminate all kinds of potential safety hazards, to eliminate all kinds of accidents in the bud! We should strengthen the ecation and training of workers in safety proction, and form a good situation in which everyone understands safety knowledge and manages safety In order to deal with all kinds of sudden major accidents, it is necessary to work out the spirit and principle of "emergency treatment and rescue plan", and deal with these accidents in an orderly way, so as not to be in a hurry and delay the battle. For this reason, the "emergency response and rescue plan for major accidents" is formulated4. All employees of our company are required to be familiar with the specific requirements of the rescue plan, and everyone can flexibly command at the scene of the accident and properly handle all kinds of accidents according to the requirements of the plan
In case of a sudden major accident, the highest leader at the scene of the accident (refers to the leader of the accident team or above) is the commander-in-chief at the scene of the accident2. The on-site commander in chief must be calm, resolute and resolute in handling matters, and immediately organize the staff to carry out the rescue work in accordance with the spirit of the rescue plan. Don't delay the best time for rescue
3. Based on the principle of "rescue first and report later", the on-site commander in chief should first organize the on-site staff to carry out rescue work, and report to the company leaders immediately after controlling the situation
4. Once the on-site situation is out of control and the company leaders cannot be contacted, the on-site commander in chief has the right to deal with all kinds of emergencies:
(1) in case of fire, call 119 for help immediately
(2) in case of personal injury and death accident, if the vehicle can not be found at the moment, the emergency center of 120 city should be immediately rescued
5. In case of an accident, all on-site staff should actively participate in the rescue work under the leadership of the on-site commander-in-chief, and should never retreat, become deserters, or refuse to obey the leadership to delay the fight. Once such incidents occur, the company will investigate the responsibility and seriously deal with them
After a sudden fire accident, the team leader of the accident team shall immediately organize the team members to put in the fire fighting work, and shall not delay the fire fighting work for any reason2. After a sudden fire accident, the non accident team operators should, depending on the severity of the fire at that time and under the unified dispatch of the on-site fire fighting commander in chief, send some personnel to help put out the fire, or take emergency power-off measures to send all personnel to help put out the fire
In case of a major personal injury accident, the team leader and the on-site operators should take decisive measures to stop the machine or cut off the power immediately, so as to rescue the victims from the machinery and equipment or the electric shock quickly If the victim lost a lot of blood, the on-site commander should immediately organize the staff to temporarily bind and stop bleeding3. If the victim's breathing and heartbeat stopped, the victim should be moved to an open space immediately, and the implementation of artificial respiration and cardiac compression resuscitation should not be delayed for half a minute and half a second
4. At this time, the on-site commander should seize the time, make an immediate decision, and urgently ask 120 City Emergency Center for help
The on-site commander should report to the company leaders in time6. In case of general personal injury accidents, the on-site commander in chief should immediately report to the company leaders, and timely find a car to send the victims to the hospital for treatment
7. When dealing with personal injury accidents, the on-site commander should deal with them promptly and safely without delay! Don't delay the best time to treat the victims! Time is life
In case of a major equipment accident, the team leader should take measures to shut down the power supply and strictly prevent the accident from expanding2. If personal injury accident occurs e to equipment accident, rescue people immediately. After rescuing the victim, start the procere of "emergency treatment and rescue plan for personal injury accident" immediately, and then deal with the equipment accident
3. After a major equipment accident, if it is not because of special circumstances such as saving people, try not to move all kinds of objects on the site, and protect the site to analyze the cause of the accident
4. After a major equipment accident, if "move" or "support" is not taken quickly; If the accident is likely to expand or endanger personal safety, the on-site commander can take these measures to deal with it. However, detailed records should be made and explained to the accident investigators so as to accurately determine the cause of the accident
5. After the occurrence of major equipment accidents, the on-site commanders should report to the company leaders immediately in case of emergency treatment
When an accident occurs, the implementation of the accident plan is completed by the emergency rescue system. The emergency rescue system is divided into two parts: the headquarters and the professional team. The chief commander of the headquarters shall be the legal representative of the enterprise. Command members should include factory proction, equipment, fire fighting and medical personnel who have the ability, responsibility, power and resources to complete a certain task. The members of the headquarters directly lead the subordinate first aid professional teams and are responsible to the General Commander, who coordinates the work of each teamCompany Leader's telephone number:
General Manager: Commander in chief of the headquarters: telephone number:
deputy commander in chief of the headquarters: telephone number:
member of the headquarters: telephone number:
member of the headquarters:
the professional team is composed of workshop supervisors. Professional team: once the accident happens, the organization rush to the scene of the accident, and implement the emergency rescue plan at the scene and the first line
According to the task, it can be divided into communication teams: to ensure the smooth broadcasting and communication between the professional teams and the general control room and the headquarters; Guide the evacuation and self rescue of personnel through broadcastingnumber: 5 Team Leader:
member list:
equipment: walkie talkie, telephone, mobile phone, loudspeaker, alarm
public security team: to maintain public security in the plant area and evacuate people and vehicles in a planned way according to the development trend of the accident
number of people: 4 team leader:
member list:
equipment: walkie talkie, telephone, mobile phone, tweeter, sign
rescue and repair team: members of the team should be familiar with the accident site, equipment and process, and repair the equipment on the premise of having protective measures, so as to prevent the expansion of the accident, rece the accident loss and inhibit the expansion of the scope of harm
number: 2 Team Leader:
member list:
equipment: protective gloves, repair tools, etc
the professional team is composed of workshop supervisors. Professional team: once the accident happens, the organization rush to the scene of the accident, and implement the emergency rescue plan at the scene and the first line
7. The emergency response and rescue plan for major accidents is the basic principle for all employees of our company in dealing with sudden major accidents. All cadres and employees of the company are required to follow the example and implement it firmly. Those who have modification opinions and supplementary opinions on the plan shall submit them to the leaders of the company as soon as possible, so that the company can timely modify the plan after summarizing the opinions1General 1.1 the preparation is based on our company's existing hoisting machinery, which is mainly used for the company's proction of hoisting and handling operations. In order to prevent major accidents of hoisting machinery from causing heavy losses to the state, collective property and indivials, rece the accident losses to the minimum, timely and effectively deal with the accidents, and restore the normal proction order as soon as possible. The emergency rescue plan was made< br /> 1.2 scope of application this plan is applicable to traffic accidents in the enterprise. 1.3 working principle (1) adhere to people-oriented. In order to ensure the safety of people's lives and property as the starting point and foothold, minimize the casualties and property losses caused by traffic accidents 2) Resume proction as soon as possible 3) Division of responsibilities should be implemented. Under the leadership of the county government and the County Quality Supervision Bureau, take the enterprise as the theme, according to their respective responsibilities, division of labor, authority and the provisions of this plan, jointly do a good job in the emergency rescue and disposal of traffic accidents 4) We should put prevention first. Actively adopt advanced prediction, prevention, early warning and emergency disposal technology to improve the level of traffic accident prevention; Constantly improve the construction of emergency rescue system, improve the technical level of rescue equipment and emergency rescue ability< br /> 1.4 responsibilities of users
The vehicle users should establish a strict responsibility system for accident prevention and emergency treatment of special equipment, earnestly perform their respective responsibilities, actively cooperate with the emergency rescue work, and ensure the normal operation of the emergency treatment work 2. Causes of crane accidents
2.1. Unscientific safety management, unsound rules and regulations, failure to operate as required, labor-saving and habitual operation< br /> 2.2 the safety distance between lifting machinery and buildings or other facilities does not meet the requirements< br /> 2.3 the operator's quality is not high, the skill is low, can't identify and predict the risk, leading to the judgment and decision-making error< br /> 2.4 incomplete safety devices or parts out of control. The stacking materials in the workplace are too high to block the sight of the crane driver. < br /> 2.5 improper selection of lifting tools and lifting points and incorrect binding method may cause objects to fall< br /> 2.6 the crane workers operate against rules and regulations< br /> 2.7 the command signal of the commander is improper or the driver receives the signal by mistake and acts by mistake< br /> 3.1 plan initiation
After receiving the accident report, the enterprise shall immediately report to the county Party committee, county government and Dazhu Bureau of quality and technical supervision. The first person in charge of the enterprise (enterprise legal person) shall approve to start the emergency plan immediately, and relevant personnel shall rush to the scene in time for emergency treatment< br /> 3.2 implementation of the plan
Equipment operators, maintenance personnel, department heads, leaders in charge and the first person in charge of safety proction shall take active and effective emergency measures according to their ties. The main responsible person of the accident unit shall not leave his post without permission ring the period of emergency rescue and accident investigation and handling< br /> < br /> 4. Accident handling proceres
4.1 establish on-site command organization< br /> Establish the on-site headquarters for special equipment accident handling (hereinafter referred to as the on-site headquarters) and implement the enterprise legal person responsibility system. The enterprise legal person is the commander in chief, the leader in charge is the deputy commander in chief, and the person in charge of each workshop is the member, who is responsible for the command and coordination of emergency rescue work after the accident. Its office is located in □ (determined by the enterprise), and the staff are responsible for the daily work. Responsibilities of the on-site headquarters: first, in case of an accident, the headquarters shall issue emergency rescue orders and signals; Second, organize and command the rescue team to carry out the rescue work; Third, timely report to the higher authorities and relevant units; The fourth is to set up an accident investigation team in time, cooperate with the superior to carry out the accident investigation, seriously investigate and collect evidence, and write relevant written materials. The main responsibilities of the on-site commander in chief are to call on the members of the on-site headquarters to study the on-site rescue plan, formulate specific rescue measures, and clarify their respective responsibilities; Be responsible for directing the emergency rescue work on site and coordinating with other rescue units or departments. The main responsibility of the on-site deputy commander in chief is to direct, organize and implement specific rescue work and assist the commander in chief< br /> 4.2 mobilize the strength to carry out the rescue work< br /> When a major accident occurs to the hoisting machinery, the personnel on the working site should take emergency measures with the sense of responsibility that the national interest is above all else, so as to minimize the possible harm caused by the accident< br /> 1. In case of major accident of lifting machinery, report to the leader of emergency rescue command center in time< br /> 2. Take effective rescue measures to minimize the accident losses and cause more serious consequences< br /> 3. Rescue the injured immediately to rece casualties< br /> 4. Protect the scene, organize rescue as required, and take safety protection measures for the staff participating in the accident emergency treatment, and work under the command of professional personnel< br /> 4.3 rescue proceres
1. After the accident, the person in charge with the highest position at the scene of the accident shall immediately command the on-site personnel to carry out the rescue work by using the available tools. If there is a wounded person, he shall immediately ask the General Hospital of the group company for help and implement the rescue< br /> 2. The person in charge at the scene of the accident shall report the progress of rescue at the scene of the accident and the emergency measures taken to the emergency headquarters of the company at any time, and start the emergency rescue plan when necessary< br /> 3. The emergency center of the company shall report the situation of the accident scene to the commander in chief at the first time, and inform other personnel of the command center to enter the post; And report the accident to the Safety Supervision Bureau of the group company; When necessary, the company's emergency rescue organization for major accidents shall be mobilized to rush to the scene of the accident and enter the state of emergency rescue< br /> 4. Emergency rescue contact number
Fire alarm: 119 emergency center: 120
Control room:
Safety Supervision Bureau:
Emergency rescue command center of the company:
Chief commander: (secretary of the Party committee) Tel.
Members of command center:
< br /> 4.4 assist to do a good job in cleaning up and statistics< br /> Assist the investigation team of relevant departments to clean up, inquire and count the property loss caused by the accident, make statistics on the death and injury, and truthfully register< br /> 4.5. Assist in the work of situation notification
it is necessary to report the situation from the top to the bottom, quickly report the situation of the accident and the progress of the accident treatment to the county government and relevant departments, and timely convey the instructions from the superior to the grassroots< br /> 4.6 assist in accident investigation
immediately after the accident, we should dispatch forces to actively cooperate with the relevant departments to assist in the investigation of the accident, and actively cooperate with the investigation team of the relevant departments in the investigation and evidence collection work, so as to ensure the authenticity and accuracy of the accident investigation< br /> 4.7 accident investigation and aftermath treatment
1. The scene of the accident should be cleaned up in time so as to resume proction as soon as possible< br /> 2. The accident unit shall analyze and discuss the accident and check the implementation of safety measures< br /> 3. The safety supervision department of the company shall review the analysis and discussion materials of the accident unit, and each unit shall organize the staff to learn and draw lessons< br /> 4. Organize and hold the company's accident notification meeting, form materials and report to the company's Safety Supervision Bureau< br /> 5. The person responsible for the accident shall be punished according to the safety management regulations, and the person with major responsibility shall be investigated for criminal responsibility 5 supplementary provisions
5.1 implementation time of the plan
the plan shall be implemented from the date of printing and distributing.